6 muncitori au sapat an 10 zile 420 metri de sant.ce lungime de sant vor sapa 10 muncitori an 8 zile avand aceeasi productivitate a muncii?
Răspunsuri la întrebare
Răspuns de
3
6 muncitori-------------------10 zile -------------------420 m
10 muncitori ----------------- 8 zile --------------------X m
-------------------------------------------------------------------------------
6 munc -------------------------10 zile ------------------420 m
10 munc ------------------------10 zile ------------------ X m
X= 10·420/6= 700 m
10 munc --------------------------10 zile ------------------700 m
10 munc ---------------------------8 zile ----------------------Y m
Y = 8·700/10 =560 m
10 muncitori ----------------- 8 zile --------------------X m
-------------------------------------------------------------------------------
6 munc -------------------------10 zile ------------------420 m
10 munc ------------------------10 zile ------------------ X m
X= 10·420/6= 700 m
10 munc --------------------------10 zile ------------------700 m
10 munc ---------------------------8 zile ----------------------Y m
Y = 8·700/10 =560 m
Valerica12311:
Dar poti s-o rezolvi prin metoda reducerii la unitate